Complete list of tasks

PROGRAM BASICS

  • After pre-construction meeting, homeowners must install permit board on their lot 8 feet from the curb.
  • After homesite is pinned (staked), spray weed killer on the foundation area.
  • Rake and remove all weeds from the foundation area after weed killer has done its job.
  • As instructed, use the hose to apply water to fill dirt inside your form boards. This aids and improves soil compaction for the foundation slab.
  • After foundation is formed, homeowners will backfill forms. Place dirt on the outside of forms.
  • After underground plumbing inspection within slab, homeowners must backfill plumbing trenches, rake and level imported fill, and remove organic debris.
  • Remove excess concrete debris and stockpile for removal.
  • Twelve hours after the slab is poured, hose down your slab for 15 – 30 minutes. This aids the curing process of the concrete. Do this each day for three days.
  • After the slab pour, homeowners will level the dirt around the perimeter of the slab with a rake and shovel. Homeowner will then build a wire cage to hold concrete trash.
  • Remove excess concrete debris and stockpile for removal.
  • After masonry is finished, rake the lot and pile all block and debris at the front of your lot after the lintel pour.
  • Remove lintel inspection plates and nails.
  • Homeowners will stack all lumber in their garages.
  • Homeowners will assist framers in installing strapping and hurricane hardware.
  • Build trash box.
  • Clean up and sweep home after framer.
  • Haul all lumber and roof shingle debris to trash box.
  • Sweep up and clean after electrical rough in.
  • Sweep up and clean after plumbing rough in.
  • Sweep up and clean after HVAC rough in.
  • Homeowners will stack all extra materials for vendor credit.
  • Dig soil away from the perimeter of the home 4 inches below the finish floor grade to prepare for DCF,“stucco.”
  • Attend mandatory paint class.
  • Seven days after the stucco is completed, clean stucco from window frames. At this time your home is ready to be primed.
  • Caulk around all exterior windows, doors and all other necessary exterior areas prior to priming.
  • Clean up drywall debris and haul to trash box.
  • Scrape drywall mud off floor.
  • Apply all primer supplied to the exterior of your home.
  • Call Florida Home Partnership staff for primer inspection.
  • Apply exterior paint to your home.
  • Call Homes for Hillsborough staff for final exterior paint inspection.
  • Back fill the sewer trench after the County sewer inspection. Use the hose to aid in compaction.
  • Install construction locks on exterior doors.
  • Caulk all interior window frames.
  • After drywall is sprayed and trim is installed, clean drywall overspray from interior window frames and other areas.
  • Caulk and putty all baseboards and door frames.
  • Prime all walls, doors, baseboards and other trim.
  • Paint ceiling with two coats of interior “ceiling white” flat paint.
  • Paint wood trim with semi gloss or high gloss paint.
  • Clean tubs, sinks, and windows. Rough cleaning will be ongoing.
  • Homeowners will attend a mandatory floor covering class.
  • Scrape and sweep floors in preparation for vinyl and carpet.
  • Install base shoe molding after vinyl installation.
  • Putty and caulk base shoe molding.
  • Paint base shoe molding.
  • Backfill driveway and sidewalk form boards.
  • Cut or fill inside of form boards to assure proper depth of either 4 or 6 inches.
  • After sidewalk and driveway pour and form board removal, fill in any voids around edges of concrete flatwork.
  • Finish final grading of lot with hand rake.
  • Install sod after final grade is completed.
  • Irrigate sod and trees for 30 days.
  • Install medicine cabinets.
  • Install interior doors locks and stops.
  • After final drywall punch, paint all drywall repairs, and detail paint.
  • Clean manufacturer marking from vinyl.
  • Vacuum carpet.
  • Perform detailed cleaning of interior.
  • Install address numbers on home.
  • Install mailbox post and box.
  • Install mini blinds.
  • Scrape and wash garage floor.
  • Sweep and pressure wash sidewalks.
  • Sweep and clean driveway, common sidewalks and curbs.

COMMON AREA TASKS

  • Remove dirt and debris from roadways, curbs and alleys.
  • Mow and weed common community areas.
  • Each week, pick up trash around perimeter of community, ponds and other common areas.
  • Remove silt buildup at storm drains.
  • Remove silt buildup inside storm basins.
  • Irrigate common landscaping.
  • Perform routine pond maintenance.